Suggested words
A winding path in the Royal Pavilion Garden

Project Timeline

  • Please note that the dates below are to be used as a guide only and are subject to change linked to planning decisions and possible conditions, as well as any conditions linked to a successful bid outcome.
  • The capital work element of the project will last for approximately one year from January 2027 to December 2027. However, the whole project will span multiple years, including project delivery of additional surveys and research, volunteer recruitment as well as the implementation of activity and interpretation plans.
A winding path in the Royal Pavilion Garden
Key Stages Dates
NLHF bid announcement December2023 /January 2024
Project start (e.g. further surveys, activity and interpretation planning and trialling etc) January/February 2024
Activity plan and engagement delivery with priority July 2025 to October 2028
RIBA Stage 4 Complete January 2026
Tender process for Garden capital works (e.g. toilets, learning space, path renewal, installation of new fence and railings etc) May – June 2026
Contractor appointed October 2026
Capital works in Garden – RIBA Stage 5 January 2027-December 2027
Capital works complete (handover and snagging) – RIBA Stage 6 January 2028-October 2028
Project completion/Project evaluation complete October 2028